Construction Information

Construction Status (through 6/30/2022)

  • Independent Living Building

    • Construction began: December 2, 2019

    • Original contract completion date: July 7, 2021

    • Contract extension completion date: October 2021

    • Total % of work completed: 100%

  • Assisted Living & Mi Casa Building

    • Construction began: January 8, 2020

    • Original contract completion date: June 26, 2021

    • Contract extension completion date: September 2021 (Delay)

    • Total % of work completed:100%

  • Healthcare Remodel - Phase I

    • Construction began: February 26, 2020

    • Original contract completion date: March 2022 (Phase I & II)

    • Total % of work completed: 100% (Phase I & II)